Maxeon Solar v Aiko Energy Germany (CFI, 29 July 2025)
| Date | 29 July 2025 |
|---|---|
| Court | CFI |
| Division | Düsseldorf (DE) Local Division |
| Type of action | Generic application |
| Registry reference | App_25845/2025 · ORD_25900/2025 |
| Parties | Memodo GmbH, Coenergia Srl a Socio Unico, PowerDeal SRL, VDH Solar Groothandel B.V., Libra Energy B.V. |
Official decision (PDF) · UPC registry entry
Dhenne Avocats represents claimants and defendants in European patent disputes before the Unified Patent Court, including the Paris divisions.
Dhenne Avocats · 10 October 2026
Our analysis
Summary
By a procedural order of 29 July 2025 (UPC_CFI_336/2024 and UPC_CFI_605/2024, App_25845/2025), the Düsseldorf Local Division (Judges Thomas, presiding and judge-rapporteur, Thom, Zhilova and Schmidt, technically qualified judge) ordered Maxeon Solar to provide, within six weeks, security of EUR 100,000 for a second group of defendants (Memodo, Libra Energy, VDH Solar Groothandel, PowerDeal and Coenergia) in its action for infringement of EP 3 065 184 against Aiko Energy and others. A first group had already obtained security in the same amount on 14 April 2025. Leave to appeal is granted.
Question
Is a late request for security by a second group of defendants admissible, and must the amount reflect those defendants’ share of the allegedly infringing sales?
Decision
It suffices that the claimant’s financial position gives rise to a legitimate and real concern that a costs order may not be recoverable or enforceable. The burden then shifts to the claimant (paragraph 14). Security may be requested at any time under Rule 158.1 RoP, so the late request is not an abuse (paragraph 15). Payment of the first security does not prove Maxeon’s financial soundness (paragraph 16). Security must not unduly restrict the right to an effective remedy (Article 47 of the Charter), but since the EUR 200,000 ceiling, for a value of EUR 2,000,000, is shared between the two groups, the burden remains reasonable (paragraphs 17 and 18). The defendants’ share of the amount in dispute is irrelevant, as each group must be able to defend itself on equal terms (paragraph 19).
Key points for practice
- Security may be sought at any stage. Where there are several groups of defendants, the costs ceiling is split between them and each may obtain its own security.
Provisions applied
- Agreement on a Unified Patent Court
- Art. 69(4)
- Rules of Procedure
- Rules 158.1, 158.4 and 355
- Case law cited
- AUDI v NST, Court of Appeal, 17 September 2024, Aarke v SodaStream, Court of Appeal, 29 November 2024, Arkyne v Plant-e Knowledge, The Hague Local Division, 13 February 2024
Related decisions
Prepared by Dhenne Avocats from the official decision, consulted on 10 October 2026. The database is updated every week, on Friday. Only the official text is authoritative.
Going further
Lexicon: Written procedure (UPC), Court fees and costs (UPC).
Source and translations
- Official source
- Unified Patent Court registry link recorded in the record
- Original language
- not recorded
- Translation available
- no translation recorded the firm’s French record is a summary, not a translation
- Date checked
- not recorded
Follow this case
Proceedings, related decisions, appeals, parties and patents as recorded in the registry and in the Dhenne Avocats corpus. Each link states its source.
Proceedings
Parties
- claimantMemodo GmbH2 decisions in the corpusFollow this party
- claimantCoenergia Srl a Socio Unico3 decisions in the corpusFollow this party
- claimantPowerDeal SRL4 decisions in the corpusFollow this party
- claimantVDH Solar Groothandel B.V.3 decisions in the corpusFollow this party
- claimantLibra Energy B.V.4 decisions in the corpusFollow this party
Decisions in the same proceedings and documented appeals
What the record states
- Nature of the act
- Generic application
- Outcome (Dhenne Avocats summary)
- Maxeon doit constituer, dans les six semaines, une garantie de 100 000 euros au profit des défenderesses 3 et 5 à 8, la demande tardive n'étant pas abusive. L'appel est autorisé.
- Appeal
- No appeal documented in the corpus, this does not mean that no appeal was lodged.
- Instance
- First-instance decision, whether it has become final is not recorded.
Patents mentioned
EP 3 065 184mentioned in: Dhenne Avocats analysis Follow this patent
Related decisions cited in the analyses
- Maxeon Solar v Aiko Energy Germany (CFI, 11 February 2026) cited in this record
- Aarke v SodaStream Industries (CoA, 29 November 2024) cited in this record
- Audi v Network System Technologies (CoA, 17 September 2024) cited in this record
- Plant-e Knowledge v Arkyne Technologies (CFI, 13 February 2024) cited in this record
Patents and standards
| Publication | Role in the dispute | Family | Standard and declaration | Pool | Sources |
|---|---|---|---|---|---|
EP 3 065 184Trench process and structure for backside contact solar cells with polysilicon doped regions recorded proprietor: Maxeon Solar Pte Ltd | Mentioned in the analysis (role not qualified) Also mentioned in 11 other decision(s): Maxeon Solar v Aiko Energy Germany (CFI, 11 February 2026) · Maxeon Solar v Aiko Energy Germany (CFI, 23 April 2025) · Maxeon Solar v Aiko Energy Germany (CFI, 14 April 2025) · Maxeon Solar v Aiko Energy Germany (CFI, 13 April 2025) · Maxeon Solar v Aiko Energy Germany (CFI, 19 February 2025) · Maxeon Solar v Aiko Energy Germany (CFI, 3 February 2025) · Maxeon Solar v Aiko Energy Germany (CFI, 21 January 2025) · Maxeon Solar v Aiko Energy Germany (CFI, ORD_60319/2024, 23 December 2 | not recorded | not recorded | not recorded | Espacenet · European Patent Register existence and title of the publication checked on 30 October 2026 (Google Patents, Espacenet and Register links are not checked automatically) mentioned in: Dhenne Avocats analysis |
Receive an alert
Weekly summary of new records and substantive updates matching what you follow. Address confirmed by email, unsubscribe at any time, one email per week even where several of your follows match.