CeraCon v Sunstar Engineering (CoA, 2 September 2025)
| Date | 2 September 2025 |
|---|---|
| Court | CoA |
| Division | Luxembourg (LU) |
| Type of action | Request for a discretionary review (RoP 220.3) |
| Registry reference | APL_35616/2025 · ORD_35966/2025 |
| Parties | CeraCon GmbH v. Sunstar Engineering Inc. |
Official decision (PDF) · UPC registry entry
Dhenne Avocats represents claimants and defendants in European patent disputes before the Unified Patent Court, including the Paris divisions.
Dhenne Avocats · 10 October 2026
Our analysis
Summary
By an order of 2 September 2025 (UPC_CoA_807/2025, APL_35616/2025), the standing judge of the Court of Appeal denied CeraCon’s request for discretionary review of the Mannheim Local Division’s order of 8 August 2025, which had refused it leave to add a new novelty attack to its counterclaim for revocation of Sunstar Engineering’s patent EP 4 108 413. The order confirms that a lack of reasonable diligence is enough to exclude an amendment under Rule 263, and that a deficient prior art search by a service provider does not excuse the party.
Question
Was the division manifestly wrong in the exercise of its discretion when it refused a new novelty attack based on Art. 54(3) EPC prior art that CeraCon’s search provider had failed to identify?
Decision
No. Leave is refused unless the applicant shows both that the amendment could not have been made earlier with reasonable diligence and that it will not unreasonably hinder the other party. Failure on diligence is sufficient (paragraphs 8 and 9). CeraCon admitted that its service provider had not found EP 3 868 480, later discovered by a patent attorney in an unrelated search, although the same search string returned it as the fifth hit (paragraph 11). Without a convincing explanation, the division did not exceed its discretion, and its order did not offend fairness, proportionality or procedural efficiency (paragraphs 12 and 13).
Key points for practice
- Practical point: a party seeking to add late prior art must explain precisely why the initial search did not reveal it, a failure by its search provider is attributed to the party.
Provisions applied
- Rules of Procedure
- Rules 220.3, 263 and 333
- European Patent Convention
- Art. 54(3)
- Case law cited
- No UPC decision is cited.
Related decisions
Prepared by Dhenne Avocats from the official decision, consulted on 10 October 2026. The database is updated every week, on Friday. Only the official text is authoritative.
Going further
Lexicon: UPC Court of Appeal.
Dhenne Avocats blog: UPC Appeals: What the Numbers Show.
Source and translations
- Official source
- Unified Patent Court registry link recorded in the record
- Original language
- not recorded
- Translation available
- no translation recorded the firm’s French record is a summary, not a translation
- Date checked
- not recorded
Follow this case
Proceedings, related decisions, appeals, parties and patents as recorded in the registry and in the Dhenne Avocats corpus. Each link states its source.
Proceedings
Parties
- claimantCeraCon GmbH3 decisions in the corpusFollow this party
- defendantSunstar Engineering Inc.Follow this party
Decisions in the same proceedings and documented appeals
What the record states
- Nature of the act
- Request for a discretionary review (RoP 220.3)
- Outcome (Dhenne Avocats summary)
- La demande de contrôle discrétionnaire est rejetée : le refus d'ajouter une nouvelle attaque en nouveauté, faute de diligence raisonnable, n'est pas manifestement erroné.
- Appeal
- Decision of the Court of Appeal.
- Instance
- Court of Appeal decision.
Patents mentioned
EP 4 108 413mentioned in: Dhenne Avocats analysis Follow this patentEP 3 868 480mentioned in: Dhenne Avocats analysis Follow this patent
Related decisions cited in the analyses
- Sunstar Engineering Europe v CeraCon (CFI, 8 August 2025) cited in this record
- CeraCon v Sunstar Engineering (CFI, 6 June 2025) cited in this record
- Centripetal v Palo Alto Networks (CFI, 19 December 2025) cites this decision
Patents and standards
| Publication | Role in the dispute | Family | Standard and declaration | Pool | Sources |
|---|---|---|---|---|---|
EP 4 108 413 | Mentioned in the analysis (role not qualified) Also mentioned in 4 other decision(s): Sunstar Engineering Europe v CeraCon (CFI, 8 August 2025) · Sunstar Engineering Europe v CeraCon (CFI, 6 June 2025) · CeraCon v Sunstar Engineering (CFI, 6 June 2025) · Sunstar Engineering Europe v CeraCon (CFI, 30 May 2025) | not recorded | not recorded | not recorded | Espacenet links not checked mentioned in: Dhenne Avocats analysis |
EP 3 868 480 | Mentioned in the analysis (role not qualified) Also mentioned in 2 other decision(s): Sunstar Engineering Europe v CeraCon (CFI, 8 August 2025) · CeraCon v Sunstar Engineering (CFI, 6 June 2025) | not recorded | not recorded | not recorded | Espacenet links not checked mentioned in: Dhenne Avocats analysis |
Receive an alert
Weekly summary of new records and substantive updates matching what you follow. Address confirmed by email, unsubscribe at any time, one email per week even where several of your follows match.