Honeywell Control Systems v Sovex Systems (CFI, UPC_CFI_575/2025, 18 September 2026)
| Date | 18 September 2026 |
|---|---|
| Court | CFI |
| Division | Mannheim (DE) Local Division |
| Type of action | Infringement Action |
| Case number(s) | UPC_CFI_575/2025 |
| Registry reference | UPC_CFI_575/2025 |
| Parties | Honeywell Control Systems Ltd. v. Sovex Systems B.V., Solvest Participatie V B.V., Solvest Participatie VI B.V., Solvest Participatie VII B.V.… |
Official decision (PDF) · UPC registry entry
Case timeline
- 22 October 2025 : Honeywell Control Systems v Sovex Systems (CFI, 22 October 2025) UPC_CFI_575/2025
- 12 February 2026 : Honeywell Control Systems v Sovex Systems (CFI, 12 February 2026) UPC_CFI_575/2025
Dhenne Avocats represents claimants and defendants in European patent disputes before the Unified Patent Court, including the Paris divisions.
Dhenne Avocats · 10 October 2026
Our analysis
Summary
In a decision of 18 September 2026, the Mannheim Local Division largely upheld Honeywell Control Systems’ infringement action on EP 2 563 695 B1 (telescopic belt conveyor) and dismissed the counterclaim for revocation. Five of the seven defendants were ordered to stop infringing in six States, to provide information, and to pay interim damages of EUR 75,000, with penalty payments and a declaration of liability for damages. Three points matter in practice: a licence defence cannot be substantiated by a bare reference to parallel national proceedings, a stay under Rule 295(m) was refused despite the contractual dispute pending in the Netherlands, and liability within the corporate group was assessed defendant by defendant.
Facts and procedure
The patent had been licensed in 2022 to a Solvest group company. The licence was terminated by letter of 13 March 2024 (paragraphs 4 to 6). The « Bendy Boom » continued to be offered, in particular by VeyorEx (formerly Sovex Systems). A dispute over the termination and an alleged 2024 licence is pending before the District Court of The Hague (paragraphs 21 and 22). Jurisdiction had been confirmed by orders of 22 October 2025 and 12 February 2026, and on 6 May 2026 the judge-rapporteur dismissed requests under Articles 29 and 30 of the Brussels I bis Regulation (paragraphs 22, 25 and 57). The defendants’ counterclaim was conditional, and the condition was held to be met (paragraph 58).
The applicable law
The panel applied Articles 25, 63, 67 and 68 UPCA on infringement and remedies, Articles 54, 56 and 138 EPC on validity, and Rules 24 (substantiation), 119 (interim award of damages), 295(m) (stay) and 354.3 (penalty payments) RoP. On the liability of persons who do not themselves perform the infringing act, it relied on the Court of Appeal’s decision in Belkin v Koninklijke Philips (paragraph 189).
Question
Was the patent valid over GB 753 and the combinations relied on, could a terminated licence, disputed before the Dutch court, defeat the action, which group companies were liable, and should the proceedings have been stayed?
Decision
Claim 1 is new: GB 753 describes an articulated boom that is expressly non-telescopic, and a statement that a feature is absent is not a disclosure of it (paragraphs 104 to 111). None of the combinations renders the invention obvious (paragraphs 121 to 172). The licence defence failed for want of substantiation, since the defendants merely referred to their Dutch pleadings without filing the exhibits (paragraphs 174 to 184). VeyorEx, Hemtech (named as manufacturer in the offer) and Solvest VII, which did not instruct VeyorEx to stop after termination, are infringers. Solvest V and Solvest VI are not (paragraphs 185 to 192). Whether the Belkin criteria extend to statutory directors was left open (paragraph 194), and a validity opinion obtained a year after termination did not exonerate them (paragraphs 196 and 197). The stay was refused because no Dutch ruling was expected soon (paragraph 203). Information is owed from 13 May 2024, the end of the 60-day notice period (paragraph 212), an accountant’s certificate was refused as disproportionate (paragraph 213). Penalty payments were set at EUR 100,000 per product or per day and EUR 5,000 per day (paragraphs 214 to 218), interim damages at EUR 75,000 (paragraphs 224 to 227) and agreed costs at EUR 175,000 (paragraph 236).
Key points for practice
- A licence defence must be substantiated before the UPC itself: referring to pleadings in parallel national proceedings does not satisfy Rule 24 (paragraphs 182 to 184).
- A contractual dispute pending before a national court does not require a stay where the UPC proceedings are well advanced and the defence is thinly substantiated (paragraph 203).
- Liability within a group is assessed company by company: being a shareholder is not enough, but failing to stop exploitation after termination can be (paragraphs 191 and 192).
- Practical point: a validity opinion obtained late does not shield directors, and the interim award under Rule 119 is measured against the expected cost of the damages proceedings (paragraphs 196, 197 and 226).
Provisions applied
- Agreement on a Unified Patent Court
- Arts 25, 63, 65, 67, 68 and 69
- Rules of Procedure
- Rules 24, 118, 119, 191, 295(m), 333 and 354.3
- European Patent Convention
- Art. 54, Art. 56, Art. 69, Art. 138
- Regulation (EU) No 1215/2012
- Arts 29 and 30
- Directive 2004/48/EC
- Art. 13
- Case law cited
- Belkin v Koninklijke Philips, Court of Appeal, 3 October 2025, Kodak v Fujifilm, Court of Appeal, 14 October 2025, Bhagat Textile Engineers v Oerlikon Textile, Court of Appeal, 9 December 2025, Sinocare v Abbott Diabetes Care, Court of Appeal, 30 March 2026, Mammut v Ortovox, Court of Appeal, 25 September 2024, Hurom v NUC Europe, Mannheim Local Division, 11 March 2025
Related decisions
Prepared by Dhenne Avocats from the official decision, consulted on 10 October 2026. The database is updated every week, on Friday. Only the official text is authoritative.
Decisions in the same proceedings
Going further
Lexicon: Patent infringement action.
Publications by Matthieu Dhenne: Pleading the Long Arm: What a UPC Statement of Claim Must Carry Beyond Jurisdiction (Kluwer Patent Blog).
Source and translations
- Official source
- Unified Patent Court registry link recorded in the record
- Original language
- not recorded
- Translation available
- no translation recorded the firm’s French record is a summary, not a translation
- Date checked
- not recorded
Follow this case
Proceedings, related decisions, appeals, parties and patents as recorded in the registry and in the Dhenne Avocats corpus. Each link states its source.
Parties
- claimantHoneywell Control Systems Ltd.4 decisions in the corpusFollow this party
- defendantSovex Systems B.V.2 decisions in the corpusFollow this party
- defendantSolvest Participatie V B.V.2 decisions in the corpusFollow this party
- defendantSolvest Participatie VI B.V.2 decisions in the corpusFollow this party
- defendantSolvest Participatie VII B.V.2 decisions in the corpusFollow this party
Decisions in the same proceedings and documented appeals
- 22 October 2025 Honeywell Control Systems v Sovex Systems (CFI, 22 October 2025) Preliminary objection · UPC_CFI_575/2025
L'exception préliminaire est rejetée : la JUB est compétente à l'égard du fabricant bosnien au titre de l'article 7, point 2, du règlement 1215/2012, et la division de Mannheim au titre de l'accessibilité de l'offre en Allemagne.
- 12 February 2026 Honeywell Control Systems v Sovex Systems (CFI, 12 February 2026) Preliminary objection · UPC_CFI_575/2025
La division locale de Mannheim rejette la demande de révision et confirme sa compétence à l'égard de toutes les défenderesses, y compris une société établie hors de l'Union au titre de l'article 71 ter du règlement Bruxelles I bis. L'appel est autorisé.
- 18 September 2026 Honeywell Control Systems v Sovex Systems (CFI, UPC_CFI_575/2025, 18 September 2026) Infringement Action · UPC_CFI_575/2025
What the record states
- Nature of the act
- Infringement Action
- Outcome (Dhenne Avocats summary)
- La division locale de Mannheim juge le brevet EP 2 563 695 B1 valable et contrefait par cinq des sept défenderesses, écarte l'exception de licence non étayée et refuse le sursis à statuer.
- Appeal
- No appeal documented in the corpus, this does not mean that no appeal was lodged.
- Instance
- First-instance decision, whether it has become final is not recorded.
Patents mentioned
EP 2 563 695 B1mentioned in: summary of the decision, Dhenne Avocats analysis Follow this patent
Related decisions cited in the analyses
- Sinocare v Abbott Diabetes Care (CoA, 30 March 2026) cited in this record
- Honeywell Control Systems v Sovex Systems (CFI, 12 February 2026) cited in this record
- Bhagat Textile Engineers v Oerlikon Textile (CoA, 9 December 2025) cited in this record
- Honeywell Control Systems v Sovex Systems (CFI, 22 October 2025) cited in this record
- Kodak v Fujifilm (CoA, 14 October 2025) cited in this record
- Belkin v Koninklijke Philips (CoA, UPC_CoA_534/2024, 3 October 2025) cited in this record
Patents and standards
| Publication | Role in the dispute | Family | Standard and declaration | Pool | Sources |
|---|---|---|---|---|---|
EP 2 563 695 B1 | Patent at issue according to the summary or official headnote Also mentioned in 2 other decision(s): Honeywell Control Systems v Sovex Systems (CFI, 12 February 2026) · Honeywell Control Systems v Sovex Systems (CFI, 22 October 2025) | not recorded | not recorded | not recorded | Espacenet links not checked mentioned in: summary of the decision, Dhenne Avocats analysis |
Receive an alert
Weekly summary of new records and substantive updates matching what you follow. Address confirmed by email, unsubscribe at any time, one email per week even where several of your follows match.